High-Rise Podium Slab Strengthening – Mumbai
Overview
A premium 60+ storey residential tower in Mumbai, with multiple towers connected through a landscaped podium, required architectural modifications. The client planned to add a canopy system, with columns resting on the midspan of the podium slab.
Challenge
The additional canopy loads created increased moment demand in the podium slab. The conventional strengthening method suggested — RC jacketing — was not feasible as it required micro-concrete pouring from the top, which was inaccessible due to the completed landscaping.
Solution
Detailed structural analysis was carried out to assess slab strength and serviceability. A CFRP laminate strengthening system was designed to enhance flexural capacity without disturbing the finished landscaping. Approval was secured from the consultant prior to execution.
Outcome
The strengthening was successfully completed in 30 days, ensuring safety, serviceability, and minimal disruption. The project demonstrated the effectiveness of advanced retrofit solutions over conventional methods.